The current status for each of the WGs and PCs will be placed here and is a living document. They are separated by group for easy perusal.
LAST UPDATE ON OCTOBER 7, 2024
Evaluation SC - Chartered
...
Our primary goal is to get our DEI plan to the EC shortly after the quarterly meeting. We were aiming for the end of the month (Sept) (
)Jira Legacy server System Jira serverId 2b19a5eb-335e-31ed-9427-a9e4284ae7b5 key ECMT-55
Community Building and Engagement SC - NOT CHARTERED
(Jay Alameda and Alana Romanella)
CB&E activities are put on hold pending further guidance from NSF as of 9/15/24
Web presence WG - NEED CHARTER APPROVED
(Dina Meek)
Updating navigation to present more of what visitors want (currently you’ll see it broken down largely by Service Team, which doesn’t mean much to visitors) - (
)Jira Legacy server System Jira serverId 2b19a5eb-335e-31ed-9427-a9e4284ae7b5 key ECMT-38 Helping people – beyond just the navigation – find the information they need as quickly as possible - (
)Jira Legacy server System Jira serverId 2b19a5eb-335e-31ed-9427-a9e4284ae7b5 key ECMT-39 As part of this work, we also updated the main access ci landing page :- (
)Jira Legacy server System Jira serverId 2b19a5eb-335e-31ed-9427-a9e4284ae7b5 key ECMT-38 Improve Website Usability - (
)Jira Legacy server System Jira serverId 2b19a5eb-335e-31ed-9427-a9e4284ae7b5 key ECMT-38
Communications SC - NEED CHARTER APPROVED
(Stephen Deems and Dina Meek)
...
Infrastructure Portfolio Expansion SC - NEED CHARTER APPROVED
(JP Navarro, Joe White)
No response as of October 7, 2024
Cybersecurity Governance Council (WG)
(Derek Simmel)
No response as of October 7, 2024
User Profile 2024 (WG)
(Derek Simmel)
No response as of October 7, 2024