The current status for each of the WGs and PCs will be placed here and is a living document. They are separated by group for easy perusal.

LAST UPDATE ON OCTOBER 7, 2024

Evaluation SC - Chartered

...

  • By the June quarterly

    • Finalize and present recommendation reports from three annual surveys.

    • Note: We may try to do this earlier next year, but it's what we did this year.

    • Present on the recommendations at the quarterly.

  • By the September quarterly

    • Review / revise (if needed) the ACCESS Evaluation Plan

    • Review / revise (if needed) the current ACCESS-wide Metrics

    • Present at the quarterly on these items

  • By the December quarterly

    • Review / revise (if needed) the ACCESS Staff Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-83
      )

    • Review / revise (if needed) the ACCESS Resource Provider Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-84
      )

    • Review / revise (if needed) the ACCESS Community Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-64
      )

    • Present at the quarterly on the survey updates

  • By the end of January

    • Distribute the ACCESS Staff Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-83
      )

    • Distribute the ACCESS Resource Provider Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-84
      )

    • Distribute the ACCESS Community Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-64
      )

  • By the end of March (i.e., in time for annual reports and panel reviews)

    • Provide results and summaries from the ACCESS Staff Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-83
      )

    • Provide results and summaries from the ACCESS Resource Provider Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-84
      )

    • Provide results and summaries from the ACCESS Community Survey (

      Jira Legacy
      serverSystem Jira
      serverId2b19a5eb-335e-31ed-9427-a9e4284ae7b5
      keyECMT-64
      )

    • Present on the survey results at the March quarterly

...

Community Building and Engagement SC - NOT CHARTERED

(Jay Alameda and Alana Romanella)

  • CB&E activities are put on hold pending further guidance from NSF as of 9/15/24

Web presence WG - NEED CHARTER APPROVED

(Dina Meek)

  • Updating navigation to present more of what visitors want (currently you’ll see it broken down largely by Service Team, which doesn’t mean much to visitors)

  • Helping people – beyond just the navigation – find the information they need as quickly as possible

  • As part of this work, we also updated the main access ci landing page:

Communications SC - NEED CHARTER APPROVED

(Stephen Deems and Dina Meek)

...

Infrastructure Portfolio Expansion SC - NEED CHARTER APPROVED
(JP Navarro, Joe White)

  • No response as of October 7, 2024

Cybersecurity Governance Council (WG)
(Derek Simmel)

  • No response as of October 7, 2024

User Profile 2024 (WG)
(Derek Simmel)

  • No response as of October 7, 2024