2026-10-05 - NSF ACO Meeting Agenda & Summary
Attendees:
John Towns, Amitava (Amit) Majumdar, Chuck Pavloski, Dina Meek, Kim Mann Bruch, Cindy Wong, Misha Shah, Sharon Geva, Ed Walker, Shannon Bradley
AI Transcribing is not allowed for this meeting due to NSF participation and their directives
Parking Lot
Decisions made during the meeting:
Use Decision Macro
Weekly ACO–NSF Meeting Structure
Items highlighted in blue are instructions for each section.
Joint Program Updates (10 min)
ACO Program Updates (5 min) - John Towns
Section content instructions: High-level summary of what changed since last week.
Metrics snapshot (usage, staffing, financials).Staffing Report - no changes
Financials - referenced in supplement
NSF Updates (15 min)
Section content instructions: NSF perspective: relevant program, agency, or portfolio updates
Any context that may affect ACCESS or ACO operations.
NSF Action Items - (5 min) https://access-ci.atlassian.net/jira/core/projects/ATT/list?sortBy=duedate&direction=ASC&filter=status%20in%20(%22To%20Do%22%2C%20In-Progress)%20AND%20%22Category%5BCategory%5D%22%20in%20(Original-PEP%2C%20PY3-PEP-WBS-5%2C%20PY3-PEP-WBS-4%2C%20PY3-PEP-WBS-3%2C%20PY3-PEP-WBS-2%2C%20PY3-PEP-WBS-1%2C%20%22NSF%20Meeting%20To%20Do%22)
Meeting tasks/Upcoming PEP TasksCarryover Action Items (5 min)
Section content instructions: Review prior week’s decisions & commitments.
Confirm closed vs. still open.
Note blockers.none
Critical Status & Red Items (10 min)
Section content instructions: Current or Overdue Tasks (top 3–5)
Owner quick updates + path to resolution.
NSF input requested if escalation/decision is needed.none
Program Spotlight (5 - 10 min) -
Section content instructions: Brief look at one priority area each week (e.g., risk, staffing, allocations, milestones).
Goal: share context and keep alignment at the program level.
Detailed work continues in ACO team meetings — this time is for big-picture feedback.Supplement Request
https://docs.google.com/document/d/1AW3Cwl4rOn_MtsO1NqWJzEfe4Y2nTDmI/edit?pli=1
no quarterly or EAB meetings in person - all virtual
the awards will still exist for PY6 - critical operation will continue for all of the awards - it depends on what we have to do for the coordination
SC/WG - may reduce some of the committees - look at them one by one - ex: we will not be re-designing the web site or making new personas
Chuck will follow up
Assistance with oversite - close out and reporting and materials for transition
should we prepare for a transition package?
Sharon - we anticipate that there will be transition planning that we will be expected to participate in - what exactly we need to hand off is currently TBD - we have a lot of the artifacts already
EC - they each got their direction of what they should do - plan for risks and possibly new ones
Communications - we may have to back off some - program stories are still important - communicate to the community what they should expect for the transition - may need more communications on that point
Sharon - transition plan - bring that up in comms - we don’t know who will be taking up comms for the new operator
John - but we don’t know who they will be
Sharon - it may that we don’t need to do anything at all - transition date end of calendar year 2027
Doesn’t know what deliverables should be - could be anywhere in the spectrum for amount to do
Formal transition date - will there be a formal switch over date - depends on what the new operator wants to prioritize first
This is making things challenging - if all we are doing is closing docs we may not need all the staff
Sharon - this is a transition and not a cutoff
But is end of 27 the beginning of overlap or the end of the overlap
End of 27 is very vague - Sharon’s thought is it depends on the new operator
When can we talk to the new people? Within months
we are in Q1 of FY27
there is a CR till Dec 11 - which comes with a prorated amount of money and a number of limitations
hopefully within a few months
EAB is beneficial for transition period
Things to support the backend - we need to keep supporting the tools
check to see what the other awards will still be using and see what we can trim down
Sharon - if there was anything we are planning to do in PY5 which doesn’t make sense because we need to find out what the plan is for the new operator - we can have a no-cost extension
John - we have targeted spending all our PY5 funds - we probably won’t need a NCE
Supplement Budget - Spending in PY5 total est between: $1,923,034.18 and $2,038,254.78
DRAFT Full Budget - $1,440,995.89
Includes SDSC ask at $276,000.00 (current levels)
Draft Full Budget: https://docs.google.com/spreadsheets/d/1NWWAdK2Y0pFo-5trJ0dOctaFaqqEixi5QHKm2cV26hU/edit?pli=1&gid=0#gid=0 - Tab 1
Draft Budget Request - Full Budget: https://docs.google.com/document/d/1xYspF88xKnqzPVhKCdqmxp4OKX9eNIl8/edit?usp=sharing&ouid=108483074521788833672&rtpof=true&sd=true
Draft Budget $750,000 with no Quarterly Meetings - includes reduction of staff - est: $778,825.43 at the moment – will reduce further to hit $750,000
Comms: Megan Johnson and Andrew Helregel - 0%
PM: Misha S - 0%
PM: Shannon Bradley - reduced to 40% from 50%
Gov: John Towns - reduced to 20%
Gov: Chuck P - 0%
Comms: Reduced Web Design Company agreement from $50,050 to $20,000
Draft Budget: $750,000 with no Quarterly Meetings - https://docs.google.com/spreadsheets/d/1NWWAdK2Y0pFo-5trJ0dOctaFaqqEixi5QHKm2cV26hU/edit?pli=1&gid=1075145002#gid=1075145002 - Tab 2
Draft Budget Request - with no Quarterly Meetings - https://docs.google.com/document/d/12GHKwqKIwGayMzL8TBc92BZsjR36OU8h/edit?usp=sharing&ouid=108483074521788833672&rtpof=true&sd=true
Draft Budget $750,000 with no PEARC, SC or Quarterly Meetings - est total $751,299.15 right now - will reduce further to hit $750,000
Comms: Megan Johnson and Andrew Helregel - 0%
PM: Misha S - 0%
PM: Shannon Bradley - reduced to 40% from 50%
Gov: John Towns - reduced to 20%
Gov: Chuck P - reduced to 25%
Comms: Reduced Web Design Company agreement from $50,050 to $25,000
Draft Budget: $750,000 with no PEARC, SC or Quarterly Meetings - https://docs.google.com/spreadsheets/d/1NWWAdK2Y0pFo-5trJ0dOctaFaqqEixi5QHKm2cV26hU/edit?pli=1&gid=2077238418#gid=2077238418 - Tab 3
Draft Budget Request - with no PEARC, SC, or Quarterly Meetings - https://docs.google.com/document/d/1UamB5hDQRch0A-sDCx8TbQhpaKgRjmfb/edit?usp=drive_link&ouid=108483074521788833672&rtpof=true&sd=true
Sharon
The number she provided is the number she has for the availble budget - prioritize accordingly - emphasis is close out and transition, de emphasize inperson travel or person
End of '27 is when the transition will be happening
There may have been activities that we intended to do in PY5 - we can still get a no-cost extension for any left-overs
This is not a PY6 - it is a transition
John
This is a challenge - that implies that there is something that will be done by the new operator at some time - but we can’t plan on a nebulous date
Sharon
We are to focus on wrapping up things
It is up to someone else to pick up things
you can’t plan on things that will be something that someone else puts together
John
Challenge is the close out and transition requires us to know what we will be transitioning to and when
Sharon
We will know sooner rather than later
Focus on the closeout
John
interpretation - we plan to shut down everything we have by the end of the award - which is not a trnsition
Sharon
She is getting varied info and interpretation
John -
Ongoing operations -
Sharon
Communications can be critical but there are other things that are not critical
PEARC and SC - beyond critical path
John
So we have to figure it out
PEARC and SC - the prior project held the booth for the next project
Sharon - don’t plan for it
John - if new operator wants to be at SC they will lose their standing
Sharon - yes
John - we will not reserve the space
Sharon - don’t worry about anyone else
John - he is worrying about the community
Sharon - the community will not be dropped
Sharon - at the limit of what she can offer for guidance
Nikki - when we go to enter a supplement - she gets a warning that supplements can only be 6 months - looks like a warning that she can still submit - but is that OK
Sharon - she thinks the people at research.gov could answer or OAM (office of award management) could help - they are pretty slammed right now but now is the best time to ask - look in award notices and Janelle Gosey (and LaShawn Farrior) is a good contact or anyone else on that would be good to email and CC Sharon
Nikki - what about a help desk ticket?
Sharon - best to start at OAM
John will find the emails for Jannele and Rashawn - Gosey, Jannele L. <jgosey@nsf.gov>, Farrior, LeVar Rashawn <lfarrior@nsf.gov>
Has to be in by Dec 1
Other ECs got similar emails and are going to probably have to commit to the new finance directive
Misha is being spinned down since we are no longer focusing on strategic planning - last week next week
Updates
Dina - sent some stories to Maria Pendleton, focused on SC
Sharon re-does her copies of the Impact page every time the page is updated - this has been very valuable
Shannon - working on PY6 supplement and budget, and starting some transition stuff
Amit - eval committee - on track to send out in January
Cindy - RAC recording will be ready soon for Sharon, EAB is Oct 28
Sharon will try to participate in the first half of the meeting - has conflict for second half
Kim - stories - UK and UM use Delta - focusing on smaller RPs and what they have been using their allocation for
Chuck - EAB meeting - Tickets for EAB recommendations - down to 12 making sure we have followed up on them - scheduling interactive meetings with EC
Sharon - remember our award ends at the end of April
John - Lesson learned - we did not formally track recommendations as early as we probably should have - need to do a better job of tracking the recommendations earlier
Lisa - still continue to be an observer - primary role going forward is helping the team process this transition - giving an outside opportunity to talk through and help make decisions and offer alternatives
Wrap-Up: Next Steps & Action Items (2–3 min)
Section content instructions: Confirm owners + deadlines.
Recap today’s decisions. - Today's Decisions (top of the agenda)
Identify materials NSF expects before the next meeting.
Additional Discussion/Update
Next Meeting: Oct 19, 2026